Thursday 19 November 2026

Government

Alberta proposes farmland ban and 600-metre setback for large data centres

Bill 42 would make near-zero-water cooling and waste-heat recovery conditions for data centre developments drawing at least 10 megawatts.

Premiers Smith and Wakeham talking in a meeting room, with photographers behind them
Photo: Canada's Premiers, Public domain, via Wikimedia Commons

Alberta’s government introduced a bill on 18 November that would keep data centres drawing 10 megawatts or more at least 600 metres from the nearest home, Bloomberg reported. The proposal is Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, an omnibus measure that also covers oil and gas cleanup, Startup Fortune reported. It would restrict where large facilities can be built and how they use water for cooling, but must pass the legislature before taking effect.

Key points

  • The proposed 600-metre distance from homes applies to data centres drawing at least 10 megawatts.
  • Bill 42 would bar large data centres from irrigated land and designated high-quality farmland.
  • Covered facilities would face near-zero-water cooling and waste-heat recovery requirements.
  • Projects already under way, including Meta’s planned Sturgeon County campus, would be exempt.

Bill 42 draws a 600-metre boundary

The distance would be measured to the nearest home. Municipalities could reduce it if the affected landowners and the Alberta Utilities Commission agree. That gives local authorities a route to accommodate a site closer to housing, but only with consent from both the people affected and the provincial utilities regulator. The proposed distance is therefore a default for covered projects rather than an absolute prohibition.

Land designated as irrigated would face a separate restriction: data centres drawing at least 10 megawatts could not be built on it. The bill would also exclude such facilities from the province’s highest-quality farmland. This designation covers roughly 14 million acres, comprising Class 1 and Class 2 land and, in municipalities without either of those classes, Class 3 land. The irrigated-land prohibition would apply in its own right, rather than depend on the quality assigned to the soil.

The two siting tests operate differently. An affected municipality could seek agreement to shorten the distance from a home, but the reported irrigated-land rule offers no corresponding reduction. A developer choosing a site would have to consider the land designation as well as its distance from housing. Both restrictions are proposals under Bill 42, not obligations already in force.

Bill 42 addresses cooling water and waste heat

The proposal extends beyond the location of a building. Under the proposal, cooling would use close to zero water, and operators would recover waste heat for greenhouses, industry or homes, according to Startup Fortune. Those provisions concern how a covered facility operates after construction, rather than which parcel it occupies. They would put cooling and heat recovery alongside land selection in the requirements a developer must address.

Startup Fortune described the cooling requirement as ruling out the cheapest evaporative setups and said waste-heat recovery would add engineering costs and connect a project to a user for the heat. Bill 42 would place the water and heat requirements in the same legislative package as the setback and farmland restrictions, giving developers several tests to meet when planning a new facility.

Meta’s Sturgeon County project is exempt

The government’s proposal follows opposition to large AI data centres. Bloomberg reported that Alberta brought forward the restrictions in response to a backlash against its efforts to attract AI infrastructure. Protesters opposed to a proposed Meta data centre gathered in Morinville on 2 August, according to the Toronto Star. Meta has proposed a one-gigawatt facility in Sturgeon County.

The bill would distinguish between developments already under way and projects subject to the proposed siting rules. Projects with permits or transmission agreements in hand would be exempt. Designated industrial areas and existing brownfield sites could be exempt from the setback, though those possible exceptions are less definite than the treatment of projects already under way.

Meta’s planned $13 billion campus in Sturgeon County, north of Edmonton, would be exempt because it is already under way.