Corvex signed a three-year, $103 million take-or-pay agreement for Blackwell computing capacity at its Mid-Atlantic 1 data centre, a deal it expects to more than double the site’s contracted annual recurring revenue from $22 million to approximately $56 million. The Nasdaq-listed GPU cloud company announced the agreement in Arlington, Virginia, on 16 November. The customer is an AI inference platform that will reserve the capacity for three years.
Key points
- Corvex says the full $103 million contract value is committed under take-or-pay terms, requiring payment whether the customer uses the reserved capacity or not.
- A $26 million customer prepayment and $38 million in committed debt financing would cover more than 80% of the approximately $78 million deployment cost, according to Corvex.
- Corvex expects revenue from the 1.6-megawatt deployment by the close of 2027’s first quarter.
- Corvex reported about $22 million in contracted annualised revenue on live compute as of 12 November, before announcing this agreement, MLQ.ai reported.
Mid-Atlantic 1 gains a 1.6-megawatt contract
Corvex says the contract calls for more than 1,000 Nvidia HGX B200 units linked by Nvidia Quantum-2 InfiniBand networking over 1.6 megawatts of IT capacity. It puts annual contract revenue for that deployment at approximately $21 million per megawatt. Under the take-or-pay terms described by the company, the customer owes payment for reserved capacity regardless of how much it uses.
The company expects contracted take-or-pay annual recurring revenue at Mid-Atlantic 1 to reach approximately $56 million once the deployment is fully in service, against $22 million on capacity already operating. That projected increase depends on delivery and acceptance of the new capacity. Corvex’s release lists equipment delivery, commissioning, customer acceptance and the customer’s payment obligations among the risks to realising the agreement’s value.
Corvex Co-Founder and Co-Chief Executive Officer Seth Demsey called this the company’s third Nvidia Blackwell deployment at Mid-Atlantic 1. Co-Founder and Co-Chief Executive Officer Jay Crystal said the agreement brings in another inference-platform customer as Corvex diversifies its customer base. The company announced an expansion of the data centre’s capacity on 31 August.
The signing follows Corvex’s third-quarter results on 12 November, when it was still negotiating an offtake agreement for a 1.6-megawatt Blackwell cluster at Mid-Atlantic 1, MLQ.ai reported. Corvex had 1.5 megawatts of live compute capacity generating about $22 million in contracted annualised revenue at that point, all under take-or-pay contracts.
Third-quarter revenue was $5 million, up 31% from $3.8 million in the second quarter, according to MLQ.ai. Corvex had secured roughly 8 megawatts of critical IT capacity for its plan, including the live capacity and space at Mid-Atlantic 1 and Midwest-1. It had reverse-merged into wearables maker Movano in March 2026 and trades on Nasdaq under MOVE.
USD.AI commits $38 million in debt
Corvex estimates the new deployment will cost approximately $78 million for GPU servers, storage, networking and spare equipment. It says a $26 million customer prepayment and $38 million in committed financing from USD.AI together cover $64 million, or more than 80% of that cost. Corvex intends to contribute the remaining $14 million.
The USD.AI commitment is for a three-year, asset-backed loan that Corvex says is non-recourse to the company. In an earlier Blackwell expansion at Mid-Atlantic 1, a Corvex subsidiary borrowed $7.5 million from USD.AI under a secured equipment facility that was also non-recourse to the parent. The new financing is a commitment, and Corvex lists closing conditions and delays in arranging funds among the risks in its announcement.
The customer prepayment puts part of the equipment cost on the buyer before the capacity begins producing revenue. The company also lists equipment procurement, facility readiness and interruptions to power or networking among the risks to deployment.
Corvex expects the deployment to be fully in service and begin generating revenue by the end of the first quarter of 2027.