Oracle said on 20 November that its OpenAI infrastructure contract was fully funded after a $20 billion capital raise earlier in the month, Reuters reported. The companies plan 4.5 gigawatts of additional US data centre capacity beyond their initial Stargate site in Abilene, Texas.
The raise comprised about $10 billion in stock and $10 billion in debt. Oracle had previously capped new financing at $20 billion at an investor day. In a post on X, Oracle said that financing, including vendor financing, was in place and described further private talks with vendors as additional options.
Oracle said its Abilene campus, where OpenAI’s GPT-6 Astra was trained, was nearly complete. The company said its next gigawatt-scale campus in Shackelford County, Texas, was fully permitted. Oracle shares rose as much as 3.3 per cent in after-hours trading.