PJM Interconnection filed its Fast Energization proposal with the Federal Energy Regulatory Commission on 16 November, seeking to cut projected study time for new power plants and transmission service for large electricity users from two years to one, according to PJM’s announcement. The grid operator serves about 67 million people across 13 states and the District of Columbia, Energy News Beat reported.
Key points
- PJM proposes studying generation and large electricity users together, with a projected one-year process in place of two years.
- States would receive the costs of transmission upgrades driven by data centres, enabling them to bill large users for those costs.
- Data-centre and corporate energy buyers warned that an annual study cycle could leave some projects waiting nearly two years.
- PJM requested a 60-day comment period and a FERC order within 120 days.
PJM combines generation and load studies
Fast Energization would bring studies of proposed generation and transmission service for large electricity users into one process. PJM says that would remove work now duplicated across separate procedures. The change concerns the time needed to study projects for reliability. It is not a timetable for building power plants, data centres or transmission lines.
PJM says its proposed process would begin with rapid screening so developers and large customers can assess a project before meeting stricter readiness and financial requirements. Those requirements would apply earlier, with PJM seeking to limit the queue to projects ready to proceed. The operator says it would retain its first-ready, first-served approach.
The proposal also sets out transmission services for large customers that bring their own generation or can reduce their demand from the grid. PJM says one option would allow interim service while network upgrades are built. The operator has said that new generation and transmission capacity are arriving too slowly to keep pace with demand growth driven mainly by large users such as data centres.
States would see data-centre upgrade costs
PJM proposes giving states access to the costs of transmission improvements driven by data centres. According to the operator, that information would enable states to bill large electricity users for those upgrades. PJM says the separate processes used for large-load transmission service have made it difficult for states to see the full costs associated with developments.
The filing addresses FERC directives concerning large loads and customers whose generation is located alongside their demand. PJM asked the regulator to allow 60 days for comments and to issue an order within 120 days. FERC’s filing library lists the proposed tariff revisions in docket ER27-531-000.
The cost question sits alongside PJM’s capacity shortfall. In July, the operator said its auction for the 2028/2029 delivery year secured 6,831 megawatts less than its reliability requirement, with a 14.7% reserve margin against a 20% target, Energy News Beat reported. That shortfall concerns future capacity. Fast Energization addresses the studies required for new projects and service.
PJM has faced a separate regulatory intervention over data-centre demand: it suspended a data-centre power auction after FERC ordered a pause, AI Affairs previously reported.
Buyers challenge PJM’s annual cycle
The Data Center Coalition and Corporate Energy Buyers Association warned PJM in an 2 October letter that combining generation and load studies could slow some connections. A large customer would first need approval from a transmission owner before joining the proposed annual PJM study cycle.
The groups said a customer approved just after the annual cutoff could wait nearly a year for the next cycle and then another year for PJM’s study. That would leave nearly two years between transmission-owner approval and completion of the PJM process. They also warned that linking a power plant to a large-load application could delay the generation project.
PJM’s proposed one-year timeline begins at the application deadline, after an early-engagement period of 14 weeks. The buyers’ objection concerns the wait before that deadline. PJM President and Chief Executive David Mills told the groups on 5 November that the proposal was still being developed, according to the same publication.
Separate rules cover data centres above 50 MW
In a separate filing on 16 November, PJM proposed rules requiring data centres of 50 megawatts or more to remain connected through specified voltage and frequency disturbances rather than switch to backup power. Nearly 3.9 gigawatts of data centres transferred to onsite generation during a disturbance on 22 July, MLQ.ai reported, citing PJM.
Under that separate proposal, new large computational loads would have to demonstrate compliance before connecting. Existing facilities would have one year from the proposed effective date of 16 January 2027, or from commercial operation if later, to comply, MLQ.ai reported.