OpenAI launches grid programme with up to 1,000 megawatts of flexibility in Georgia

OpenAI intends to use its planned Effingham County campus as a pilot for arrangements under which utilities could call for reductions in power demand.

Sam Altman speaking onstage against a purple TechCrunch Disrupt backdrop.
Photo: TechCrunch, CC BY 2.0, via Wikimedia Commons (cropped)

OpenAI launched its Grid Protectors Program on 2 November with an agreement for up to 1,000 megawatts of flexible electricity demand at its planned campus in Effingham County, Georgia. In a company announcement, OpenAI said the Georgia arrangement would be a pilot for working with utilities, regulators and policymakers to reduce demand at future compute campuses when local grids are under strain.

Key points

  • OpenAI says its Georgia Power agreement allows for up to 1,000 megawatts of demand reduction, equivalent to the average electricity demand of roughly 700,000 households.
  • OpenAI has committed to cover the infrastructure and electric-service costs of its planned Effingham County campus.
  • Georgia Power projects approximately $950 million in annual customer savings from 2029 across a portfolio of large-load agreements and expected growth that includes the OpenAI project, according to OpenAI.
  • OpenAI said in July that it was contracting for 3.2 gigawatts of electricity for the Georgia project, with deliveries phased between 2028 and 2032, The Energy Mag reported.

Georgia agreement allows 1,000 megawatts of flexibility

The agreement with Georgia Power covers up to 1,000 megawatts of flexible demand response: electricity use the campus can reduce when the utility needs capacity for other customers. OpenAI says that amount is equivalent to the average demand of roughly 700,000 households. The Effingham County campus remains in development, and OpenAI intends to use it as the programme’s pilot.

OpenAI said it would work with utilities at future sites to agree how much power a campus could stop drawing, how quickly it could do so and how long a reduction could last. Those arrangements would reflect local grid conditions. The company also plans to design future facilities so they can cut consumption when required.

Where equipment and local needs permit, OpenAI says it will work with grid operators on power from on-site generation or storage. It also plans to use batteries and power controls to manage changes in demand. OpenAI cited a projection that US data centre capacity would exceed 100 gigawatts by 2030.

Project Camellia bears its infrastructure costs

OpenAI has committed to pay the full infrastructure and electric-service costs required for the Effingham County site, known as Project Camellia. In July, the company said it was contracting with Georgia Power for 3.2 gigawatts of electricity for the development, The Energy Mag reported. That supply is to be delivered in phases between 2028 and 2032.

OpenAI said in July that state regulatory rules prevented the project’s infrastructure and electric-service costs from being passed to existing ratepayers, according to The Energy Mag. OpenAI also pledged $80 million for local benefits over the project’s duration and yearly public checks by an external organisation.

Georgia Power expects its deals with large electricity users, alongside projected growth, to save customers approximately $950 million a year from 2029, with Project Camellia among those deals, according to OpenAI’s announcement. Georgia Power forecasts at least $15 in monthly savings for a typical residential customer consuming 1,000 kilowatt-hours. Those projections cover the utility’s broader portfolio, rather than the OpenAI agreement alone.

Grid Protectors arrangements will vary by campus

OpenAI says the programme will seek arrangements suited to each utility’s grid. It describes campus electricity demand as a way to contribute to fixed grid costs when capacity is available, while reducing consumption during periods of strain. The company also says flexibility cannot replace investment in new electricity supply and transmission.

The company says long-term contracts and financial assurances can protect other electricity customers if a campus is delayed, reduced or cancelled. It plans to work with utilities, regulators and policymakers on commitments for future sites and to share those commitments as they are finalised.

OpenAI has also announced a deal for approximately 8 gigawatts of IT capacity at Ohio’s PORTS-Pike Technology Campus, with SB Energy, Nvidia and the US Department of Energy involved. SB Energy is to build, own and operate that facility under a 20-year lease to OpenAI. OpenAI said its first 800 megawatts were expected to become available in 2028.

Sources

Topics: Data centres, Energy